Grid Filmstrip Single Slideshow
Download
Loading...

Photos

Nov 2015 Patio cladding and grilles
Nov 2015 Staircase Hostel
October 2015 terrace tiling
October 2015 cladding training block
October 2015 waterproofing
Sept 15 Tailoring classroom
Sept 15 Entrance conference block
Sept 15 Flooring in academic block
Sept 15 Facade with cladding complete
Sept 15 Classroom sponsored by Magneti Marelli
Sept 15 Overhead grille in patios
Sept 15 some windows and grilles in place
Campus view April 2015
Cladding front work April 2015
Cladding rear April 2015
Canopy Academic March 15
Brick tile cladding Mar 15
Water Harvesting Pipeline Mar 15
Interior Patio March 15
July 2015 cladding academic
Parapet and cladding Oct 14
Raising columns Oct 14
Shaft Work Nov 14
Academic Block Jan 15
Front view Nov '14
Collonade to hostel Dec 14
View from East Sept 14
Academic Block Aug '14
Brickwork in classroom July 14
June '14
June '14
June '14
June '14
June '14
May '14
May '14
May '14
April 2014
April 2014
Mar '14
Mar '14
Mar '14
Jan 14 steel bent for last columns
Jan 14 hostel block
Dec 13 -roof on Academic block
Dec 13 Academic block seen from above
Nov 13 Brickwork coming up on ground floor
Nov 13 staircase cast
Nov 13 Columns raised for first floor
Location Sohna Road
Nov 13 - entrance shade cast
Nov 13 - curing of roof of academic block with water
Nov 13 - casting work going on
Oct 13 Shuttering for hostel block
October 2013 - Casting Academic block ceiling
October - Total of 8 trucks for Academic Block
Basement after brickwork
Preparing for casting Academic Block Oct 13
Conduiting Academic Block Oct 2013
Setting Pillars for first floor October 2013
October 2013 Casting ceiling of Academic Block
Sept 2013 - Shuttering for Academic Block
August - Tying up the beams Academic Block
August - Removing shuttering central Block
Columns in central block
August - curing ceiling conference block
Raising columns for Academic Block
August - Shuttering for entrance
Steel work on roof of Block C
Plinth Beams after casting Academic Blcok
July 13 Shuttering for First Floor
July 13 filling of plinth
June 13 Inside central basement
June 13 Columns being raised for hostel block
June 13 - Small Classroom Building
June 13 - Academic block basement
June 13 frame for plinth beams
May 2013 View of site
April 2013 view of basement roof
April 2013 Steel work basement roof
March 2013 casting work
March 2013 casting of basement walls
February 2013 Columns and Footings
Building Sanction Plan displayed at site
January 2013 Raft of basement
Column Footings January 2013
HBS Contractor team and EDI Site Engineer
December 2012 excavation
December 2012 Excavation begins
November 2012 Groundbreaking
Soil testing May 2012
Five acre site for Kamalini
Stop slideshow
                                                          Classroom   Academic Courtyard Hostel Block Academic Block                                                                                   Standing water is curing the cement                     in January 2013     EDI Vice President M de Souza with architect E Pradhan and contractor H Bhalla   SAMSUNG DIGITAL CAMERA
Powered by FastMail